Resurfacing for Portadown Road


A RESURFACING scheme for Portadown Road, Armagh - delayed since August - is scheduled to get underway on Monday, 2 October. The improvement work will extend for 0.9 kilometres from the junction with Drumadd Road to the junction with Drummanmore Road and includes resurfacing with upgrading of road drainage and footway repairs.
A RESURFACING scheme for Portadown Road, Armagh - delayed since August - is scheduled to get underway on Monday, 2 October.
The improvement work will extend for 0.9 kilometres from the junction with Drumadd Road to the junction with Drummanmore Road and includes resurfacing with upgrading of road drainage and footway repairs.
To help ensure the safety of those using the road and to facilitate the works it will be necessary to operate overnight road closures, from 8pm to 6:30am commencing on Monday 2 October to Monday, 16 October. The road will be open during daytime hours.
An alternative route will be signed with traffic being diverted via A3 College Hill, A3 Rokeby Green, A3 The Mall West, A51 Gaol Square, A51 Barrack Hill, A51 Hamiltonsbawn Road, B111 Annareagh Road, B131 Legacorry Road and A3 Portadown Road.
Local access for residents and emergency services will be maintained although some minor delays may be experienced.
Road users are advised to allow extra time for their journey and to follow the alternative routes which will be clearly signed on the approaches to the closure.
Completion of the work by 16 October 2023 is dependent on favourable weather conditions. The Department will keep the public informed of any change.